grounding transformer main body in nude , the accessories packing in seaworthy standard wooden case
Port
Shanghai or Ningbo port
You May Like:
furnace transformer power transform er oil immersed transformer wind generator transformer
transformer substation dry type transformer distribution transformer Rectifier Transformer
Product Description
Main Function And Features
110kV oil-immersed OLTC Power Transformer grounding transformer
1
Power transformer 220kv 110kv and 66kv low-loss series
2
low loss, low noise, high reliability
3
Iron core is made of cold-rolled silicon-steel
4
Have good ability withstand short-circuit
5
The oil tank is bell type with the structure of full folding plate type,
6
Having an excellent exterior and easy for maintenance
7
Adopting capsule-type oil container, it can reduce oil aging to the lowest degree
8
Power loss: no-load loss is 30% lower than that of IEC standard
9
Reliability: All in-service product have no damages or oil leakage occurred
Core
1
Power transformer core is made of high-permeable grain-orientated top quality cold-rolled silicon sheet
2
The material is cut with advanced Germany Geoge GmbH automatic shear line with the cut burrs controlled within 0.02mm.
3
Power transformer silicon sheet fabrication adopts “no-upper yoke-lapped’ technology and all lapped joints of the silicon sheet are 45 full-miters
4
Effectively improves no-load performance and reduces noises.
Coil
1
The high-voltage(HV) coil adopts an interleaved-continuous structure to improve the voltage characteristics under impact voltage and make voltage evenly distributed.
2
All stays and pads are chamfered to keep highly reliable insulation.
Oil tank and accessories
1
Power transformer tank wall adopts wide steel sheet
2
Which will be folded into corrugated structure without splicing
3
In this way welds aredecreased and mechanical strength is enhanced
4
The corrugated wall has diverging effect, and thus plays arole in decrease of noise.
Technical Parameters
Power transforer main Technical Parameters for 110kVpower transformer Level S(F)S9, S(F)S10, S(F)S11 Series
power transformers three-phase three winding no-load-tap-changing power transformer:
Packaging & Shipping
PACKING AND SHIPMENT FOR TRANSFORMER
Our Services
1.
Pre sale service
a.
make technical solution
b.
send quotation, technical data sheet and drawing
c.
prepare power transmission plan, testing plan,and shipment plan
2.
In sale service
a.
supervise the manufacturing schedule totally in accordance with the plan
b.
send photos to customer during every manufacturing process(hold point)
c.
inform the customer one week before testinng.
3.
After sale service
a.
installation and commissioning
b.
training the workers
c.
quick response within 12 hours any time
d.
provide 12 months gurantee period normally.
INSTALLATION AND COMMISSIONING (OVERSEA)
Company Information
FAQ
1. Q:
What is your minimum order quantity?
A:
1 set.
2. Q:
What is your delivery time ?
A:
Depend on the type of transformer.
3. Q:
What is your payment term?
A:
30% advance by T/T , 70% before delivery by T/T or L/C or we can discuss about it.
4. Q:
What kind of starndard you follow?
A:
IEC, ANSI, CSA, GB, etc
5. Q:
What kind of supporting documentation you can provide normally
A:
Quotation,outline drawing,manufacturing plan, quality control plan testing plan, financial report, type test report(KEMA, CESI),reference list,etc
6. Q:
What is your normal wanrranty period?
A:
12 months after transformer operation.
7. Q:
Can u do installation and commissioningin user's site?
A:
Yes, we can send our installation team to user's country for service.
8. Q:
Do you have any experience in this kind of transformer?